Plug-in solar became legal in the UK in August 2026, but qualified electricians raised a question: do standard UK residual current devices respond fast enough if something goes wrong? UK electrician Cory Mac went to Germany, where plug-in solar has been sold for years, and ran the tests to find out.

Helpful video reference. Cory Mac's video "Why Every Electrician is Worried about THIS" documents his hands-on residual current protection tests carried out in Germany. Cory Mac is a UK electrician and solar installer with a YouTube channel covering practical electrical and solar topics for tradespeople and homeowners.

What SI 2026/848 actually changed

From 27 August 2026, connecting an ENA-approved plug-in solar inverter to a standard UK socket is legal without an MCS certificate, DNO notification, or planning permission. The key conditions: the inverter must be on the ENA register, output must not exceed 800W, and the socket must be a permanent fixed socket (not an extension lead). The law does not change the rules for hardwired installations, consumer unit work, or anything that connects to the grid for export via a generation meter.

1. Why UK electricians raised safety questions

When SI 2026/848 passed, some qualified electricians pointed out that plug-in inverters inject AC power back into the socket wiring. If the inverter develops a fault, the question is whether the residual current device on that circuit trips fast enough to prevent harm. This is not a theoretical concern: RCDs exist precisely to protect people from shock on circuits where unexpected current flows.

2. The Germany residual current test

Germany has allowed plug-in solar (Balkonkraftwerk) for several years, so there is a larger evidence base there. Cory Mac travelled to Germany to test actual trip times under fault conditions using plug-in inverters sold in that market. His measurements showed trip times of around 23.5 milliseconds. The threshold for serious injury from electrical shock is generally taken as 300 milliseconds. The devices passed by a large margin.

3. UK vs Germany: what the regulations require

German Balkonkraftwerk regulations already required built-in Type A residual current monitoring inside the inverter itself, so the device detects and interrupts a fault before it reaches the socket. The UK's SI 2026/848 rules require that any kit placed on the ENA approved register meets equivalent technical safety criteria. If you buy a kit from the ENA register, it has been assessed against those criteria. Buying a cheap inverter from outside the register and plugging it in is a different matter.

4. Check your home's RCD or RCBO protection first

Before connecting any plug-in solar unit, open the consumer unit cover (or ask an electrician to check) and confirm that the socket circuit has RCD or RCBO protection. Most homes rewired or built after 2008 have this. Older boards with fuse wire or MCBs only, and no RCD, provide no residual current protection. In that case, the board needs upgrading before you install plug-in solar. Consumer unit work always requires a Part P-registered electrician.

Quick checklist before connecting plug-in solar

  • ENA register: Confirm the kit is on the ENA approved list before buying.
  • RCD protection: The socket circuit must be protected by an RCD or RCBO at the consumer unit.
  • Fixed socket: Connect to a permanent fixed socket, not an extension lead or adaptor.
  • Under 800W: Total output from all plug-in inverters in the property must not exceed 800W per phase.
  • Consumer unit work: Any wiring changes inside the consumer unit require a Part P-registered electrician.

5. What still needs a qualified person

The plug-in connection itself does not need a qualified electrician. But adding RCD protection to an older board, running a new socket circuit, or doing any work on the incoming mains always does. These are notifiable works under Part P of the Building Regulations: a registered electrician must carry them out and issue a certificate. Never attempt consumer unit or mains work yourself, whatever you read online.

Frequently Asked Questions

Does plug-in solar need MCS certification in the UK?

No. Under SI 2026/848, connecting an ENA-approved plug-in solar kit to a standard socket does not require MCS certification, planning permission, or DNO notification. MCS certification is only required for hardwired grid-connected systems that export electricity, such as rooftop installs with a generation meter and SEG contract.

What is the ENA register for plug-in solar?

The Energy Networks Association maintains a list of approved plug-in solar inverters that meet the safety and technical requirements of SI 2026/848. Only kits on this register can be connected to UK sockets under the simplified rules without additional checks. Connecting a non-registered unit may still be possible under other regulations, but requires further assessment.

Is plug-in solar safe in older UK homes?

It depends on the consumer unit. If the socket circuit is protected by an RCD or RCBO, an ENA-registered plug-in solar kit is safe. Older homes with no residual current protection at the consumer unit present a higher risk. The board should be upgraded before installing any plug-in solar, and that upgrade must be done by a Part P-registered electrician.