MCS installation
Real-World Solar PV Install: Artisan Electrics and Oval Renewables
Seeing a full MCS-certified solar installation from start to finish is one of the clearest ways to understand what the process actually involves. This video from Artisan Electrics documents a collaboration install with Oval Renewables, covering the whole job from roof survey to energised system.
Helpful video reference. Artisan Electrics' install documentary "Artisan Electrics and Oval Renewables Solar PV" shows a real residential MCS installation from start to finish. Artisan Electrics is a UK electrical and solar installation channel with over 300,000 subscribers.
1. Pre-install survey and system design
Every MCS installation begins with a survey. The installer checks the roof's structural condition and load-bearing capacity, assesses orientation and pitch, and identifies any shading from chimneys, dormers or neighbouring buildings. The output is a detailed system design: panel layout, inverter model, expected yield and a formal quote.
The survey also establishes which DNO notification route applies (see step 4), and flags any consumer unit upgrades needed before the solar connection can be made. For most standard 3-bed semis, the existing consumer unit is usually fine; older properties with ageing boards sometimes need a board replacement as part of the job.
2. Scaffolding and roof mounting
Scaffolding goes up first so the roof team can work safely. Rails are fixed directly to the rafter structure through the roof tiles using weatherproofed flashing brackets. Getting the bracket positions right at this stage is critical: they determine the panel layout and the structural integrity of the array in high winds.
Panels click onto the rails using clamps. A well-organised two-person team typically completes the roof work in a single day for a standard 10-14 panel domestic system. The roof is left weathertight at the end of each day, with temporary covers if the inverter wiring hasn't been connected yet.
3. DC cabling, inverter and consumer unit connection
Once the panels are on the roof, DC cables are run from the array down into the property to the inverter location, usually inside the loft or in a utility room. The inverter converts the solar DC output into standard AC mains power. It also handles grid export and, if batteries are fitted, charges and discharges them.
The inverter AC output connects to the consumer unit via a dedicated AC isolator and MCB. This part of the installation involves working inside the consumer unit and on live mains circuits. It must be done by a qualified electrician and forms part of the MCS certification.
What's included in an MCS install package
- MCS certificate: Required for Smart Export Guarantee registration and 0% VAT eligibility.
- EPC-linked declaration: Confirms the installation meets MCS standards.
- DNO notification: G98 self-notification or G99 application handled by the installer.
- Electrical Installation Certificate: Covers the AC consumer unit connection.
4. DNO notification and commissioning
Before the system can export to the grid, the DNO (Distribution Network Operator) must be notified. For most domestic systems up to 3.68 kW (16A per phase) with no battery export, this is a G98 self-notification: the installer notifies the DNO within 28 days of commissioning, and work can begin straight away.
Larger systems, systems with battery export, or anything connecting at higher voltages need G99. That is a formal application that can take up to 45 working days, and the system cannot be energised until the DNO approves it. Your installer will confirm which route applies and handle the paperwork as part of the MCS package.
Once the DNO process is complete, the system is commissioned: the installer checks all connections, verifies output, and sets up the monitoring app. You can then register for the Smart Export Guarantee (SEG) with your electricity supplier to earn export payments.
Frequently Asked Questions
How long does a solar PV installation take?
Most residential solar PV installations take one to two days on site. The roof work and inverter wiring typically complete in day one; consumer unit connection, testing and commissioning follow. Scaffolding erection and removal add extra time around the install days.
What is G98 and G99 notification?
G98 is the self-notification process for small grid-connected solar systems up to 3.68 kW (16A per phase) with no battery export. G99 applies to larger systems or those with battery export, and requires a formal application to the DNO that can take up to 45 working days. Your installer will advise which applies and handle the paperwork.
Can I connect the solar inverter to the consumer unit myself?
No. Connecting the inverter to the consumer unit involves working in the consumer unit and on mains AC wiring, which must be done by a qualified electrician. It also forms part of the MCS certification, which requires an MCS-certified installer to sign off the whole system. Attempting it yourself invalidates the certification and the warranty.