Panel installation and wiring
Ground Mount Solar on Challenging Ground: Lessons from Two Norfolk Projects
Building a ground-mounted solar array on firm, dry land is straightforward. Building one on a former bog in Norfolk is not. Two real projects from Artisan Electrics reveal the ground conditions, foundation choices, and practical problems that rooftop installers never have to face.
Helpful video reference. Artisan Electrics' case study "We Built Solar on an Ancient Bog... Big Mistake?" walks through two real ground mount projects in Norfolk, including the ground condition problems they encountered. Artisan Electrics is a Cambridge-based solar and electrical contractor with over 300,000 YouTube subscribers.
MCS and planning: what ground mounts require
Any grid-connected ground-mounted system must be MCS-certified. DNO notification is mandatory before energising: G98 for systems up to 16A per phase with no battery export, G99 for everything larger. Ground-mounted arrays above 9 square metres may need planning permission, depending on location and land type. A qualified MCS-certified installer manages both the notification and the certification.
1. Survey the ground conditions before anything else
The first question for any ground mount is what the ground will actually hold. Boggy or marshy land, like the Norfolk sites in Artisan Electrics' video, may look firm in dry weather but compress or shift under a loaded mounting structure over winter. A basic soil survey before design can save significant cost later, since the choice of foundation type affects everything from materials to labour to timeline.
2. Choose the right mounting structure for the soil type
Standard concrete anchor blocks work well on firm, free-draining ground. Softer soils need driven steel piles or ground screws, which distribute load over a greater depth rather than relying on surface friction. Very wet or boggy sites may need reinforced concrete ground beams spanning between piles, particularly for larger arrays. The installation cost per kilowatt goes up considerably once you move away from anchor blocks, so get this confirmed before quoting panels and inverters.
3. Plan cable routing carefully on a large rural site
The cable run from the array back to the building (and from there to the inverter, consumer unit, and any battery) can cover tens of metres on a rural property. Underground runs need appropriate burial depth, armoured cabling rated for direct burial or draw-through conduit, and water-resistant connections at both ends. On a wet site, any low point in the cable route can collect water: a slope towards the building at the trench exit prevents ingress. This is work for a qualified electrician, not a DIY job.
4. Understand planning permission and permitted development
Ground-mounted solar may fall under permitted development in England if the array is below 9 square metres in footprint, no higher than 4 metres, and not on certain designated land types (conservation areas, listed buildings, Areas of Outstanding Natural Beauty, and similar). Larger arrays, or those on restricted land, need a full planning application. Check with your local planning authority before ordering equipment: approval can take weeks, and a refused application wastes survey costs.
What made the Norfolk bog sites difficult
- Ground movement: Waterlogged peat and clay compress seasonally, which can shift mounting posts if not founded deep enough.
- Drainage: Cable trenches through boggy ground need extra waterproofing at all entry and exit points.
- Access: Large plant (excavators, concrete delivery vehicles) may not be able to reach the installation area without hardstanding or matting.
- Electrics: Any work connecting the array to a consumer unit or existing wiring inside a building must be carried out by a qualified electrician.
5. Commission and sign off properly
Once the array is built, test the structure for movement before wiring up. Check all cable entry points for water ingress, verify correct polarity on every string, and confirm the inverter is reading generation before the MCS certificate is issued. The MCS certificate is what unlocks Smart Export Guarantee (SEG) payments, so it cannot be issued for a system that has not been properly commissioned and inspected.
Frequently Asked Questions
Can you install ground-mounted solar on boggy or marshy land?
Yes, but it requires specialist mounting solutions. Standard concrete anchors will not hold in waterlogged or soft ground, so the installation needs driven piles, ground screws or reinforced concrete ground beams instead. A soil survey before the design stage avoids expensive changes later.
Do ground-mounted solar panels need planning permission in the UK?
Ground-mounted arrays may fall under permitted development rights if they are below 9 square metres, no higher than 4 metres, and not installed on certain types of land. Larger or more complex installations need a full planning application. If you are unsure, check with your local planning authority before ordering equipment.
What is the DNO notification process for a ground-mounted solar system?
Any grid-connected solar installation, whether roof-mounted or ground-mounted, must be notified to the Distribution Network Operator before it is energised. Systems up to 16A per phase with no battery export use the simpler G98 form. Larger systems or those with export from batteries use G99, which requires pre-approval and can take several weeks.